Relining pipes at CJP Chemicals
Customer:
CJP Chemicals Gauteng
System:
20 meter long, 160mm diameter earthenware sewer line running 2 meters deep under parking lot.
Situation:
The sewer pipe had cracks in multiple sections causing constant blockages. Replacing the pipe would mean digging up the driveway and parking lot causing disruption to CJP Chemicals daily operations.
Solution:
Nu Flow cleaned out the 160mm pipe and then relined the pipe with Nu Flow’s structural lining technology which created a “nu pipe” within the original damaged pipe. The cleaning and lining was done by working from manholes thereby causing no damage nor disruptions to the driveway and parking lot. The job was done in 1 day which is incomparable faster than a traditional pipe replacement.