Nu Flow re-lines cracked storm water pipe

Location:
Kloof rd, Sea point, Western Cape, South Africa

Situation:
Nu Flow technicians were called to secure a leak that was causing resultant damage to one of the units below. Upon inspection Nu FLow found that this was caused by a crack in the storm water system. Traditional pipe replacement methods were not an option as the pipe runs within the balcony slab. Replacing the pipe would result in major damage to the balcony. The owner turned to Nu FLow for a better solution.

Solution:
Nu FLow used Nu Flow’s pull-in-place structural re-lining system to re-line the damaged pipe working from existing access points thereby causing no damage to the balcony.

The end result is a new pipe with-in the original pipe.

No Mess, no chopping open, damage to structures!